Successful Completion of Centralized Maintenance on the Jiangxi Section of the Beijing-Kowloon Railway

?Published:2023-09-21 ?【字體:??

      The 1-kilometer-long replacement track on the Jiangxi section of the Beijing-Kowloon Railway took 130 days to complete. This maintenance project represents the longest centralized construction time for the Jiangxi section of the Beijing-Kowloon Railway since its opening.

    An additional maintenance project on CR-Nanchang’s Yingtan Railway mobilized more than 100 large-scale track maintenance machines and over 3,000 workers to work along the 731-kilometer-long Jiangxi section of the Beijing-Kowloon Railway.

    According to data, from May 5 to September 11, the Yingtan Railway maintenance section saw a total of 100.8 kilometers of mechanized ballast cleaning, 38 kilometers of mechanized sleeper replacements, and 206 kilometers of track replacements. This significantly improved the quality of the railway tracks and ensured the safe operation of trains.